Clayton Ridge Board

By: KCTN News
Dec 7th, 2017

THE CLAYTON RIDGE SCHOOL BOARD APPROVED A LOAN AMOUNT OF NEARLY 3.74-MILLIONS FOR THE SCHOOL RENOVATION PROJECT.

THE BOARD ALSO APPROVED A NUMBER OF BIDS FOR CONSTRUCTION OF THE PROJECT. THE BIGGEST ITEMS INCLUDE 106-THOUSAND FOR DEMOLITION AND GRADING OF THE 1903 BUILDING. 222-THOUSAND FOR CONCRETE WORK, 186-THOUSAND FOR MASONRY, 158-THOUSAND FOR STEEL FABRICATION WORK, 146-THOUSAND FOR ROOFING AND SHEET MEDAL. IT ALSO INCLUDES 1.1-MILLION FOR PLUMBING AND HVAC WORK AND NEARLY 299-THOUSAND FOR ELECTRICAL. FOR THE ENTIRE LIST, LOG ON TO KCTN.COM, CLICK ON THE NEWS TAB.

Clayton Ridge Board summary as follows:

1)  Approved the hiring of Bob Sweers as middle school volleyball coach for 2018-2019
2)  Approved the PPEL loan structure proposal as follows:
Fidelity Bank & Trust, Peoples State Bank and Community Savings Bank submitted a combined bid for a total loan amount of $3,735,000
        to be funded on 7/1/18, with Fidelity taking on the full amount of the note initially, and than participating out 1/3 of the note to Peoples State Bank
        and another 1/3 to Community Savings Bank.  The loan will be a 9-year term & amortization at a 3.00% tax exempt fixed rate for the duration of the loan.
3)  Approved a payment to BLDD in the amount of $57,139.58.
4)  Approved the following recommended low bids as submitted for the construction project:
   Demolition & Grading of the 1903 building: Tricon Construction    $106,000
   Concrete: Tricon Construction      222,000
   Masonry: Darold Berger Masonry        186,000
   Steel Fabrication & Erection : Tricon Construction      158,000
   General Trades: Portzen Construction      842,000
   Roofing & Sheet Metal: T&K Roofing & Sheet Metal 146,185
   Glazing: Zephyr Aluminum        47,340
   Flooring: Commercial Flooring        25,220
           Fire Suppression: Midwest Auto. Fire Sprinkler  42,920
   Plumbing & HVAC: Winona Controls    1,115,000
   Electrical:                 A & G Electric       298,675
           Elevator:         O’Keefe Elevator Co.       107,300

5)  Approved the following alternates:
   Admin. area addition: $194,228
   Environmental graphics:       8,797
   Additional MEP scope:   316,152
   Boys showers:     18,635
   Commons storage area:     47,474